Performance on Tunnel Construction

Client
Major Construction Group
Country
Netherlands
Year
2002
Industry
Construction & Transportation
Service
Risk Management, Operations & Asset Performance

A construction company had to bore a 15 m diameter tunnel for a high-speed train line in an environmentally sensitive area. A kwantis consultant developed a schedule risk model to evaluate its criticalities.

The challenge

The tunnel’s schedule had to fit with contiguous line developments, and these interfaces needed special attention.

Our approach

The kwantis consultant applied a risk and performance management approach that included:

  • the evaluation of uncertainties
  • project progress measurement with Earned Value Management
  • the evaluation of acceleration scenarios

A dedicated probabilistic model focused on the performance of the tunnel boring machine (TBM), to estimate its future performance.

The outcome

The project ended ahead of schedule, in line with the probabilistic schedule estimates. As a result, the company extended the risk and performance approach to other similar projects.

Related case studies

How can we help you?

Tell us about your project, asset or data challenge. Our consultants and engineers will get back to you.

Get in touch

Quick links

↑ ↓ to navigate ↵ to open All results

Send us a message

We will get back to you shortly.

Protected by reCAPTCHA: the Google privacy policy and terms apply.