Project Risk Management

Naval Construction Risk Assessment

Client
Major Oil & Gas Operator
Country
France, Norway, Korea
Year
2003-2004
Industry
Construction & Transportation
Service
Risk Management

Two of the main Korean shipyards shared the construction of the largest FPSO ever built. A kwantis partner carried out a detailed schedule and cost risk assessment of the work.

The challenge

One yard was building the topside modules, the other the hull and the integration of the modules. Shipbuilding and topsides integration of giant facilities for a deep offshore project involves several challenges:

  • demanding interfaces between contractors
  • fast-track construction
  • technical complexity
  • bottleneck management of dry-dock and offshore commissioning

Our approach

The work started from the project risk register, with interviews of project and contractor experts directly in the yards. A detailed probabilistic model was then built, integrating time and cost uncertainties.

The outcome

Integrating time and cost uncertainties uncovered the project criticalities. The model assessed the relative criticality of each work package, and was used to re-evaluate the investment contingencies and to develop an acceleration plan based on incentive and penalty schemes.

Related case studies

How can we help you?

Tell us about your project, asset or data challenge. Our consultants and engineers will get back to you.

Get in touch

Quick links

↑ ↓ to navigate ↵ to open All results

Send us a message

We will get back to you shortly.

Protected by reCAPTCHA: the Google privacy policy and terms apply.